Our schedule is weather dependent, but we are making every effort to keep the campus comfortable in this ever-changing New England climate.
If you have a question regarding the following schedule, please call the Work Order Center at Extension 2-3048.
The following buildings will be ready by April 24, 2009:
• Bapst Library
• Carney Hall
• Higgins Hall
• Corcoran Commons
• McElroy Hall
• Merkert Center
• McGuinn Hall
• O’Neill Library
• Waul House
The following buildings will be ready by May 1, 2009:
• Robsham Theatre
• St. John’s Seminary
• Campion Hall
• Devlin Hall
• Gasson Hall
• Lyons Hall
• Cushing Hall
• Law Library
• Fulton Hall
The following buildings will be ready by May 8, 2009:
• Alumni House
• 21 Campanella Way
• Connolly House
• Conte Forum
• Yawkey Center
• Hovey House
• More Hall
• St. Clement’s
• 3 Lake St
The following buildings will be ready by May 15, 2009:
• Edmonds Residence Hall
• Voute & Gabelli Residence Halls
• Vanderslice Residence Hall
• 90 St. Thomas More Residence Hall
• 110 St Thomas More Residence Hall
• Walsh Residence Hall, 7th & 8th floor lounges and 1st floor Dining Area